This open house was active from Jan. 22-31, 2021. Information on this website may no longer be current.
Email us
for more information.
The timeline below is subject to change.
Survey and studies
Winter 2019-winter 2020
Preliminary designs
Spring 2019-spring 2020
Permitting
Winter-summer 2020
Open house
April 6-26, 2020
Final design
Spring-summer 2020
Contractor bid process
November 2020
Construction kickoff (current status)
Jan. 22-31, 2021
Start of construction
Jan. 25, 2021
Project completion (tentative)
September 2021