  • Survey and studies

    Winter 2019-winter 2020
  • Preliminary designs

    Spring 2019-spring 2020
  • Permitting

    Winter-summer 2020
  • Open house

    April 6-26, 2020
  • Final design

    Spring-summer 2020
  • Contractor bid process

    November 2020
  • Construction kickoff (current status)

    Jan. 22-31, 2021
  • Start of construction

    Jan. 25, 2021
  • Project completion (tentative)